Saturday, June 21, 2014

Update

The parking lot is graded out and will be ready for asphalt Tuesday weather permitting. 



The 33 unit is nearly complete and we will be putting the final touches on next week. 





The 28 unit is dried in and rough mechanicals are well under way. We will be ready for insulation late next week. 








Tuesday, June 17, 2014

Parking lot update

The curbs were poured yesterday. Tomorrow and Thursday the lot will be graded out for asphalt on Friday.