Monday, September 29, 2014

Completion

Landing building B opened up on 9/12. 

The landscaping for the project is complete. 










Wednesday, July 30, 2014

Update

The 2nd floor is drywalled. We will be prepping for paint next week. 

First floor mechanicals are roughed in and we are insulating.  

The exterior is a little over 50% complete. 










Saturday, June 21, 2014

Update

The parking lot is graded out and will be ready for asphalt Tuesday weather permitting. 



The 33 unit is nearly complete and we will be putting the final touches on next week. 





The 28 unit is dried in and rough mechanicals are well under way. We will be ready for insulation late next week. 








Tuesday, June 17, 2014

Parking lot update

The curbs were poured yesterday. Tomorrow and Thursday the lot will be graded out for asphalt on Friday. 




Tuesday, May 20, 2014

The Landing - Update

The exterior is coming along well. Most of the masonry is complete and the siding is off to a good start. 


The 3rd floor - most of the solid surface is installed and kitchen and bath cabinets are being installed. 



The 28 unit - trusses are set and 35% of the roof is sheathed. We will begin shingling the roof early next week.